NOVEMBER 11, 2017

Progress:

Capitol Paving of DC (the contractor) continued the work along Kennedy Street NW between Georgia Ave NW and North Capitol Street NW. The contractor installed 1.29 square yards of 6 inch PCC sidewalk, 70 square yards brick sidewalk on PCC base, 29 Cubic yards PCC alley-driveway entrance and 54 linear feet for the circular granite curb. Capitol Paving also continued work at 100 block for the bio-retention area and installed 536 linear feet of underdrain PVC 4” pipe, 13 linear feet of underdrain PVC 6” pipe, 22 linear feet of underdrain connection pipe 6” and 3 Under-Drain Cleanout Covers in Landscape. Capitol paving also installed about 100 square yards of Geotextile for Stormwater Management and 100 Square yards of Waterproof Membrane for Stormwater Management. Jaxson Point (Capitol Paving’s sub-contractor) performed the electrical work and installed 3 – 3section traffic signal heads, 9 ball LED module 12 inch and 2- 8 ft. Mast Arm. 


NOVEMBER 4, 2017

Progress:

Capitol Paving of DC (the contractor) continued the work along Kennedy Street NW between Georgia Ave NW and North Capitol Street NW. The contractor installed 73 square yards of 4 inch PCC sidewalk, 16 square yards of 6 inch PCC sidewalk and 61 square yards brick sidewalk on PCC base. Capitol Paving also continued work at 100 block for the bio-retention area and poured concrete for alley driveway entrance, poured 356 linear feet of valley gutter, 61 linear feet of PCC mountable curb and 3.5 linear feet of circular granite curb. Jaxson Point (Capitol Paving’s sub-contractor) performed the electrical work and installed about four (4) 20 feet traffic signal poles, twelve (12) 28.5 feet light pole with 8’ arm, and 1traffic signal heads.